Skip to content

Construction Updates

Project Update

Construction is active across segments 1 through 12 of the VIA Rapid Green Line corridor, with coordination efforts in place to help minimize conflicts and service interruptions. Expect intermittent lane and sidewalk closures, as well as detours along the corridor. Some work will occur during nighttime hours to minimize traffic disruptions and increase safety. Motorists, cyclists and pedestrians are encouraged to use caution in and around construction zones.

Key takeaways, as of September 1:

– Segment map has been transitioned from 8 segments to 12
– Included an emphasis on upcoming turning access closures along San Pedro, Olmos, Santa Monica, Wildwood, Langton, Thames
– Segment 6 and 10 lane closures starting 8/31, and 9/1

Last Modified: September 1, 2026

Sign up to receive the
latest construction updates

Project Update
Construction is active across segments 1 through 8 of the VIA Rapid Green Line corridor. Crews continue to advance both above and underground utility adjustments along all segments, with coordination efforts in place to help minimize conflicts and service interruptions. Expect intermittent lane and sidewalk closures along the corridor. Some work will occur during nighttime hours to minimize traffic disruptions and ensure safety. Motorists, cyclists, and pedestrians are encouraged to use caution in and around construction zones.

The projected construction dates within the map below are estimates and may be impacted by inclement weather or other unforeseen circumstances that could cause project delays.
Last Modified: May 16, 2026

About the VIA Rapid Green Line

Planned to open in Spring 2028, the VIA Rapid Green Line project will provide fast, reliable service.  The new bus line will run north and south along San Pedro Avenue, from the San Antonio International Airport to downtown, and on to Brooks Transit Center.  It will connect riders to key residential areas, job centers, schools and cultural landmarks. For more information on VIA’s Rapid Green Line, please visit the project’s homepage. 

See how construction will have an impact on the corridor.
VIA Rapid Green Line corridor map showing construction segments 1 through 12. Select a segment for closure details.

Corridor Segments to Streamline the Project

The corridor has been divided into segments. Construction may happen in several segments at the same time, with work coordinated to help minimize traffic impacts between nearby areas.

Construction Overview

Underground and overhead utility relocations

New sidewalks and driveways near bus stations and intersections

New bus station foundations

Intersection improvements

Individuals and businesses along the San Pedro corridor can expect construction impacts between 2025 and 2027. The project involves new bus stations and improved infrastructure in key areas of the project corridor along San Pedro Avenue, between U.S. Highway 281 and Isom Road to Roosevelt Avenue and Steves Avenue.

Along the Green Line corridor, existing stations will be replaced with either new side-running or center-running stations. This project also includes the addition of new sidewalks, ramps, curbs, gutters, and drainage systems.

Preliminary Design Features

0 +

new signalized pedestrian crossings

0 +

intersections with upgrades and synchronized signals for improved traffic flow

0 +

new or replaced stormwater drains, along with other drainage improvements

0 +

miles of new and repaired sidewalks

Construction Timeline

Summer 2026

Fall 2026

Construction, including sidewalk and station foundation work, will begin along the corridor in key areas.

Construction continues with multiple segments under active construction.

If you are having trouble viewing the above map in your browser or on your mobile device, click here to view to the map in full screen.

Events

Some text here to explain and invite community to events.

There are no scheduled events.
Please check back soon.

Reach out to Us

Visit Our ART Project Office

Visit VIA’s Green Line project office at 7067 San Pedro Avenue to learn more about VIA Rapid Green Line, ask questions, and give feedback. View project office location and hours.

Frequently Asked Questions

How long will construction last?

The type of construction work and duration planned along the corridor will vary depending on the amount of infrastructure improvements planned along specific segments or intersections. However, our goal is to complete the work as efficiently as possible, and we will continue to share updates as they become available with the community. The Federal Transit Administration’s Revenue Service date for this project is April 2028.

In some locations, the work involves complex tasks such as moving utilities, upgrading infrastructure, and ensuring everything meets safety and quality standards. Our team is working hard to complete the project efficiently while minimizing disruption as much as possible.

We will provide 90-day general construction updates and 30-day construction activity forecasts with specific planned work. The monthly and quarterly updates will be posted on the VIA Rapid Construction Web Page.

Some of the existing utilities will be moved and/or replaced to accommodate improvements, improving future access, reducing service disruption and supporting long-term infrastructure reliability.

To learn more, visit this page for updates or contact us at [email protected] and (210) 362-2590. The community is also invited to visit the Green Line Project Office, located at 7067 San Pedro Ave., during the following days and times:
• Monday, Thursday, and Friday from 8 a.m. – 5 p.m.
• Tuesday and Wednesday from 8 a.m.- 7 p.m.
• The first Saturday of each month from 9 a.m. – 1 p.m.

Support Businesses

Project Update
Last Modified: May 16, 2026

segment 3 & 4

San Pedro Avenue

St. Mary’s Street & Navarro Street

Last modified: September 1, 2026

Segment 3 — St. Mary's Street (southbound) Segment 4 — Navarro Street (northbound)

Scope

Includes Green Line roadway and station improvements performed under a southbound lane-closure construction phase. The current FHJV schedule identifies a 141-day southbound lane-closure duration for this segment.

Segment 3 — St. Mary's Street (southbound)

Upcoming Construction Activity

San Pedro Avenue at Basse Road

Impact: Lane closure
Begins: August 24, 2026

Ongoing Construction Activity

Fresno Street at San Pedro Avenue

Impact: Daily closure
Duration: Through TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Segment 4 — Navarro Street (northbound)

Upcoming Construction Activity

San Pedro Avenue at Basse Road

Impact: Lane closure
Begins: August 24, 2026

Ongoing Construction Activity

Fresno Street at San Pedro Avenue

Impact: Daily closure
Duration: Through TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 1

Roosevelt Avenue

Steves Avenue and Eagleland Drive

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work from service drop poles to cabinets. Construction is phased through northbound and southbound lane closures to complete the corridor improvements.

Upcoming Construction Activity

Roosevelt Avenue between Steves Avenue and Eagleland Drive

Impact: TBD
Scheduled Dates: TBD

Ongoing Construction Activity

Roosevelt Avenue between Steves Avenue and Eagleland Drive

Impact: Northbound Lane closure(s)
Duration: 7/16/26, anticipated through 2/19/27

Roosevelt Avenue onto McKinley Avenue

Impact: Detour (turn access closed)
Duration: 5/15/26, anticipated through 9/1/26

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 5

San Pedro Avenue

N St. Mary’s Street and Navarro Avenue

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements, sanitary, water, and storm utility work and electrical work, followed by phased northbound and southbound construction.

Upcoming Construction Activity

N St. Mary’s Street and Navarro Avenue to Warren/Maverick and San Pedro Avenue

Impact: TBD
Begins: TBD

Ongoing Construction Activity

N St. Mary’s Street and Navarro Avenue to Warren/Maverick and San Pedro Avenue

Impact: Northbound Lane closure(s)
Duration: 7/7/26, anticipated through 12/9/26

San Pedro Avenue onto Euclid Avenue – Northbound and Southbound

Impact: Detour (turn access closed)
Duration: 7/7/26, anticipated through 9/11/26

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 7

San Pedro Avenue

TBD

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction is sequenced through northbound and southbound lane-closure phases.

Upcoming Construction Activity

TBD

Impact: TBD
Scheduled Dates: TBD

Ongoing Construction Activity

TBD

Impact: TBD
Duration: Through TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 8

San Pedro Avenue

Hollywood Avenue and Asbury Ln


Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements, sanitary, water, and storm utility work and electrical work. Construction progresses through southbound and northbound lane-closure phases, followed by a traffic shift for construction within the middle work zone. 

Upcoming Construction Activity

San Pedro Avenue onto Santa Monica Street – Northbound and Southbound

Impact: Detour (turn access closed)
Scheduled Dates: 9/4/26, anticipated through 11/26/2026

San Pedro Avenue onto Olmos– Northbound and Southbound

Impact: Detour (turn access closed)
Scheduled Dates: 9/4/26, anticipated through 11/26/2026

Ongoing Construction Activity

San Pedro Avenue between Hollywood Avenue and Asbury Ln

Impact: Southbound Lane closure(s)
Duration: 7/1/26, anticipated through 3/8/27

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 10

San Pedro Avenue

Basse Road and Oblate

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction progresses through northbound and southbound lane-closure phases, followed by a traffic shift to complete construction within the middle work zone.

Upcoming Construction Activity

San Pedro Avenue between Basse Road and Oblate

Impact: Southbound Lane closure(s)
Scheduled Dates: (TCP set date) 9/1/26, anticipated through 12/9/26

Ongoing Construction Activity

San Pedro Avenue between Basse Road and Oblate

Impact: TBD
Duration: TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 12

Isom Road

San Pedro Avenue to Isom Road

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction is sequenced through southbound and northbound lane-closure phases to complete the corridor improvements. 

Upcoming Construction Activity

San Pedro Avenue between Loop 410 and Lockhill and Isom Road/ US281

Impact: TBD
Scheduled Dates: TBD

Ongoing Construction Activity

San Pedro Avenue between Loop 410 and Lockhill and Isom Road/ US281

Impact: Road and/or Lane Closures/Detours
Duration: From 7/6/26, anticipated through 12/14/26

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 11

San Pedro Avenue

San Pedro Avenue between Oblate and Loop 410

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction is phased through northbound and southbound lane closures, followed by a traffic shift to accommodate construction within the middle work zone.

Upcoming Construction Activity

San Pedro Avenue onto Langton Drive – Northbound

Impact: Detour (turn access closed)
Scheduled Dates: (TCP set date) 9/3/26, anticipated through 11/25/26

San Pedro Avenue onto Thames Drive – Northbound

Impact: Detour (turn access closed)
Scheduled Dates: (TCP set date) 9/3/26, anticipated through 11/25/26

Ongoing Construction Activity

San Pedro Avenue between Oblate and Loop 410

Impact: Southbound Lane closure(s)
Duration: From 8/3/26, anticipated through 11/12/26

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 9

San Pedro Avenue

Asbury Ln and Basse Rd


Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction progresses through southbound and northbound lane-closure phases, followed by a traffic shift to accommodate construction within the middle work zone.

Upcoming Construction Activity

San Pedro Avenue onto West Wildwood Drive – Northbound and Southbound

Impact: Detour (turn access closed)
Scheduled Dates: 9/2/26, anticipated through 11/24/26

Ongoing Construction Activity

San Pedro Avenue between Asbury Ln and Basse Rd

Impact: Northbound Lane closure(s)
Duration: From 7/2/26, anticipated through 12/1/26

San Pedro Avenue onto West Mandalay Drive

Impact: Detour (turn access closed)
Duration: TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 6

San Pedro Avenue

Warren/Maverick and Russel Pl

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements along with sanitary, water, and storm utility work and electrical work. Construction progresses through southbound and northbound lane-closure phases, followed by a traffic shift to complete improvements within the middle work zone.

Upcoming Construction Activity

San Pedro Avenue between Warren/Maverick and Russel Pl

Impact: Southbound Lane closure(s)
Scheduled Dates: (TCP set date) 8/31/26, anticipated through 3/29/27

Ongoing Construction Activity

San Pedro Avenue onto West Evergreen Street – Northbound

Impact: Detour (turn access closed)
Duration: Through TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.

segment 2

San Pedro Avenue

TBD

Last modified: September 1, 2026

Scope

Includes Green Line roadway and station improvements, sanitary, water, and storm utility work, and electrical work from service drop poles to cabinets. Construction is planned through separate southbound and northbound lane-closure phases.

Upcoming Construction Activity

TBD

Impact: TBD
Begins: TBD

Ongoing Construction Activity

TBD

Impact: TBD
Duration: Through TBD

Project Progress

Construction progress, August 2026

Progress photos coming soon.

Schedules are subject to change.